B.E.S.T.™ Mat Installation Guide

Roll over the step text to see the photo that goes with that step.


Step 1: Tools needed: square, razor knife, tape measure, screwdriver, caulk gun.
Step 2: Level floor, remove large rocks.
Step 3: Roll floor for solid compaction.
Step 4: Roll mat out, measure, and cut.
Step 5: Roll mat out in stall, and butt edges.
Step 6: Custom cut-out posts.
Step 7: Insert seam protector into both sides of mat.
Step 8: Pull top of seam protector back and apply G.E. Silicone 2801 between seam and protector and mat. Repeat on other side. (Two tubes per side.)
Step 9: Apply weight to top of seam protector to spread silicone out. Wipe excess away.
Step 10: Apply 6" to 10" bedding. (Extra bedding is recommended for agressive shoes.)